Special Report on Demolition Blasting of 104 Meters High Building in Zhongshan City, Guangdong Province

Special Report on Demolition Blasting of 104 Meters High Building in Zhongshan City, Guangdong Province

(Summary description)Editor'snote:   ThePeakGardenwasbuiltin1994andwascappedin1997.The34-storeybuildingis344.1metershigh.Itisaframe-supportedshearwallstructure.Itisthetallestbuildingdemolishedbydomesticblastingandhasappliedtobecomethe"Asia'sfirstexplosion".Oneofthefewhigh-risebuildings. ThePeakGardenwasappliedforblastinginFebruarytoofficialblastingonAugust13.Thetimewasupto6months.Thedayswearelookingforwardtoarefinallycoming,andIwishtheChinesepeopleasuccessfulblast!   Joyaftersuccessfulblasting    Figure1   FigureII   Successfulblastingofthetopgarden    PreparetoblastChenShaopantoprovidepictures    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess   ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess  ChenShaopanprovidespicturesoftheblastingprocess   ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess   ChenShaopanprovidespicturesoftheblastingprocess   "Asia'sfirst-explosion"trackingreport-   Unfinished15yearsofplanning   "Asia'sfirstexplosion"     ——Theblastingofthe104.1mhighbuildingofShijiePeakGardeninZhongshan,Guangdong   "Five,four,three,two,one,detonation!"   At10:30onthemorningofAugust13,withtheorderofLiuWen,thechairmanofthesmashingengineeringheadquartersofShijiePeakGarden,thestaffofGuangdongZhongrenGroupConstructionCo.,Ltd.Pressedthepulsedetonatorinyourhand. "嘣,嘣,嘣..."18consecutiveloudnoises,afterashort3.6seconds,atotalheightof104.1meters,atotalof34layersofZhongshanShijiePeakGardenunfinishedbuildingsweighingtensofthousandsoftonsofbody,oneSuddenly,hesuddenly"squats"andsuddenlyrushestowardthewestsideoftheopenspace. Thethreehigh-poweredfireenginesthathavebeenwaitingforalongtimeimmediatelysprayedahugeamountofwatermist,andcarriedout“interceptioninterception”onthedust“whitesmoke”causedbytheexplosion,andsprinkledwatertoreducedust. Congratulationsontheheadquartersofthemeetingroomonthe4thfloorofShunjingGarden,andthesimpleviewingplatformsetuponthebalconyburstintoapplause. Atthispoint,theblastingprojectofthePeakGarden,whichisknownasthe"Asia'sNo.1Blast",wasacompletesuccess. Afterthat,itwillenterthedemolitionandclean-upphaseforupto50days.   ItisunderstoodthatthetopofthehillgardenislocatedinthesouthsideofZhongshanCollege,DongchengDistrict,ZhongshanCity,ZhongshanCity,ontheeastsideofthesnowroad,willbebuiltintheStarCityBuilding. Thebuildingtobeexplodedis104.1meters,withatotalof34floors(including1basement),33.8meterswidefromeasttowest,38.5meterslongfromnorthtosouth,and27875squaremeters. Thebuildingisframe-supportedshearwallstructure,arrangedina“well”shape.The1stfloorandthebasementareframestructures,the2-32floorsareshearwallstructures,andthemiddlepartisthecoretube. Theeastsideofthebuildingis44metersawayfromthebottomoftheslope,thesoutheastsideis40metersawayfromDongyueTemple;thesouthsideis5.2metersawayfromthewall,only6metersawayfromthenearestresidentialhouse;thewestsideis81metersawayfromthebottomoftheslope. Thebuildingwasbuiltin1994andwascappedin1997. Forvariousreasons,thebuildinghasnotbeenofficiallyputintouse.IthasbeenrenamedasthePeakGarden,YangmingMountainVilla,StarCity,andZhongshanCity,butithasneverbeenabletogetridofthefateofthe"unfinished". InJune2007,thebuildingwastransferredtoZhongshanChangjiangZhaoyeRealEstateDevelopmentCo.,Ltd.asawhole. InordertocopewiththeoverallplanningdevelopmentofZhongshanCity,acceleratethepaceofrenovationoftheoldcity,andaccordingtothecompany'sprojectplanningneeds,decidedtouseblastingdemolition,theplotwillberebuiltafterthedemolition.   OnFebruary25,commissionedbythePublicSecurityBureauoftheMinistryofPublicSecurity,theGuangdongProvincialPublicSecurityDepartmentandtheZhongshanPublicSecurityBureau,theChinaEngineeringBlastingAssociationhostedareviewmeetinginBeijingonthe“BlastingDemolitionProjectoftheUnfinishedBuildingoftheShijiazhuangPeakGardeninZhongshanCity”.TheexpertgroupledbyWangXuguang,academicianoftheChineseAcademyofEngineeringandchairmanoftheChinaEngineeringBlastingAssociation,listenedtothebriefingandreviewrequirementsoftheProvincialPublicSecurityDepartmentandtheMunicipalPublicSecurityBureauontheblastingproject,andintroducedtheconstructionplanoftheGuangdongZhongrenGroup.Afterquestioninganddiscussion,thereviewopinionswereputforwardandtheMunicipalPublicSecurityBureauwasapprovedtoapprovetheconstructionoftheproject. Inordertoensurethesafetyandsuccessoftheblastingdemolitionproject,theZhongshanMunicipalGovernmenthasspeciallysetupacoordinationheadquarters,whichisresponsiblefort

Special Report on Demolition Blasting of 104 Meters High Building in Zhongshan City, Guangdong Province

(Summary description)Editor'snote:   ThePeakGardenwasbuiltin1994andwascappedin1997.The34-storeybuildingis344.1metershigh.Itisaframe-supportedshearwallstructure.Itisthetallestbuildingdemolishedbydomesticblastingandhasappliedtobecomethe"Asia'sfirstexplosion".Oneofthefewhigh-risebuildings. ThePeakGardenwasappliedforblastinginFebruarytoofficialblastingonAugust13.Thetimewasupto6months.Thedayswearelookingforwardtoarefinallycoming,andIwishtheChinesepeopleasuccessfulblast!   Joyaftersuccessfulblasting    Figure1   FigureII   Successfulblastingofthetopgarden    PreparetoblastChenShaopantoprovidepictures    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess   ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess  ChenShaopanprovidespicturesoftheblastingprocess   ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess   ChenShaopanprovidespicturesoftheblastingprocess   "Asia'sfirst-explosion"trackingreport-   Unfinished15yearsofplanning   "Asia'sfirstexplosion"     ——Theblastingofthe104.1mhighbuildingofShijiePeakGardeninZhongshan,Guangdong   "Five,four,three,two,one,detonation!"   At10:30onthemorningofAugust13,withtheorderofLiuWen,thechairmanofthesmashingengineeringheadquartersofShijiePeakGarden,thestaffofGuangdongZhongrenGroupConstructionCo.,Ltd.Pressedthepulsedetonatorinyourhand. "嘣,嘣,嘣..."18consecutiveloudnoises,afterashort3.6seconds,atotalheightof104.1meters,atotalof34layersofZhongshanShijiePeakGardenunfinishedbuildingsweighingtensofthousandsoftonsofbody,oneSuddenly,hesuddenly"squats"andsuddenlyrushestowardthewestsideoftheopenspace. Thethreehigh-poweredfireenginesthathavebeenwaitingforalongtimeimmediatelysprayedahugeamountofwatermist,andcarriedout“interceptioninterception”onthedust“whitesmoke”causedbytheexplosion,andsprinkledwatertoreducedust. Congratulationsontheheadquartersofthemeetingroomonthe4thfloorofShunjingGarden,andthesimpleviewingplatformsetuponthebalconyburstintoapplause. Atthispoint,theblastingprojectofthePeakGarden,whichisknownasthe"Asia'sNo.1Blast",wasacompletesuccess. Afterthat,itwillenterthedemolitionandclean-upphaseforupto50days.   ItisunderstoodthatthetopofthehillgardenislocatedinthesouthsideofZhongshanCollege,DongchengDistrict,ZhongshanCity,ZhongshanCity,ontheeastsideofthesnowroad,willbebuiltintheStarCityBuilding. Thebuildingtobeexplodedis104.1meters,withatotalof34floors(including1basement),33.8meterswidefromeasttowest,38.5meterslongfromnorthtosouth,and27875squaremeters. Thebuildingisframe-supportedshearwallstructure,arrangedina“well”shape.The1stfloorandthebasementareframestructures,the2-32floorsareshearwallstructures,andthemiddlepartisthecoretube. Theeastsideofthebuildingis44metersawayfromthebottomoftheslope,thesoutheastsideis40metersawayfromDongyueTemple;thesouthsideis5.2metersawayfromthewall,only6metersawayfromthenearestresidentialhouse;thewestsideis81metersawayfromthebottomoftheslope. Thebuildingwasbuiltin1994andwascappedin1997. Forvariousreasons,thebuildinghasnotbeenofficiallyputintouse.IthasbeenrenamedasthePeakGarden,YangmingMountainVilla,StarCity,andZhongshanCity,butithasneverbeenabletogetridofthefateofthe"unfinished". InJune2007,thebuildingwastransferredtoZhongshanChangjiangZhaoyeRealEstateDevelopmentCo.,Ltd.asawhole. InordertocopewiththeoverallplanningdevelopmentofZhongshanCity,acceleratethepaceofrenovationoftheoldcity,andaccordingtothecompany'sprojectplanningneeds,decidedtouseblastingdemolition,theplotwillberebuiltafterthedemolition.   OnFebruary25,commissionedbythePublicSecurityBureauoftheMinistryofPublicSecurity,theGuangdongProvincialPublicSecurityDepartmentandtheZhongshanPublicSecurityBureau,theChinaEngineeringBlastingAssociationhostedareviewmeetinginBeijingonthe“BlastingDemolitionProjectoftheUnfinishedBuildingoftheShijiazhuangPeakGardeninZhongshanCity”.TheexpertgroupledbyWangXuguang,academicianoftheChineseAcademyofEngineeringandchairmanoftheChinaEngineeringBlastingAssociation,listenedtothebriefingandreviewrequirementsoftheProvincialPublicSecurityDepartmentandtheMunicipalPublicSecurityBureauontheblastingproject,andintroducedtheconstructionplanoftheGuangdongZhongrenGroup.Afterquestioninganddiscussion,thereviewopinionswereputforwardandtheMunicipalPublicSecurityBureauwasapprovedtoapprovetheconstructionoftheproject. Inordertoensurethesafetyandsuccessoftheblastingdemolitionproject,theZhongshanMunicipalGovernmenthasspeciallysetupacoordinationheadquarters,whichisresponsiblefort

Information

Editor's note:

 

  The Peak Garden was built in 1994 and was capped in 1997. The 34-storey building is 344.1 meters high. It is a frame-supported shear wall structure. It is the tallest building demolished by domestic blasting and has applied to become the "Asia's first explosion". One of the few high-rise buildings. The Peak Garden was applied for blasting in February to official blasting on August 13. The time was up to 6 months. The days we are looking forward to are finally coming, and I wish the Chinese people a successful blast!

 

  Joy after successful blasting

 

贵州爆破网

 

  Figure 1

 

贵州爆破网

 

 Figure II

 

  Successful blasting of the top garden

 

贵州爆破网

 

  Prepare to blast Chen Shaopan to provide pictures

 

贵州爆破网

 

  Chen Shaopan provides pictures of the blasting process

 

贵州爆破网

 

  Chen Shaopan provides pictures of the blasting process

 

贵州爆破网

 

 Chen Shaopan provides pictures of the blasting process

 

贵州爆破网

 

  Chen Shaopan provides pictures of the blasting process

 

贵州爆破网

 

Chen Shaopan provides pictures of the blasting process

 

贵州爆破网

 

 Chen Shaopan provides pictures of the blasting process

 

贵州爆破网

 

  Chen Shaopan provides pictures of the blasting process

 

贵州爆破网

 

  Chen Shaopan provides pictures of the blasting process

 

贵州爆破网

 

  Chen Shaopan provides pictures of the blasting process

 

贵州爆破网

 

  Chen Shaopan provides pictures of the blasting process

 

贵州爆破网

 

  Chen Shaopan provides pictures of the blasting process

 

贵州爆破网

 

  Chen Shaopan provides pictures of the blasting process

 

贵州爆破网

 

  Chen Shaopan provides pictures of the blasting process

 

贵州爆破网

 

  Chen Shaopan provides pictures of the blasting process

 

贵州爆破网

 

  Chen Shaopan provides pictures of the blasting process

 

贵州爆破网

 

  Chen Shaopan provides pictures of the blasting process

 

贵州爆破网

 

  Chen Shaopan provides pictures of the blasting process

 

贵州爆破网

 

 Chen Shaopan provides pictures of the blasting process

 

  "Asia's first - explosion" tracking report -

 

  Unfinished 15 years of planning

 

  "Asia's first explosion"

 

 

 

  ——The blasting of the 104.1m high building of Shijie Peak Garden in Zhongshan, Guangdong

 

  "Five, four, three, two, one, detonation!"

 

  At 10:30 on the morning of August 13, with the order of Liu Wen, the chairman of the smashing engineering headquarters of Shijie Peak Garden, the staff of Guangdong Zhongren Group Construction Co., Ltd. Pressed the pulse detonator in your hand. "嘣, 嘣, 嘣..." 18 consecutive loud noises, after a short 3.6 seconds, a total height of 104.1 meters, a total of 34 layers of Zhongshan Shijie Peak Garden unfinished buildings weighing tens of thousands of tons of body, one Suddenly, he suddenly "squats" and suddenly rushes toward the west side of the open space. The three high-powered fire engines that have been waiting for a long time immediately sprayed a huge amount of water mist, and carried out “interception interception” on the dust “white smoke” caused by the explosion, and sprinkled water to reduce dust. Congratulations on the headquarters of the meeting room on the 4th floor of Shunjing Garden, and the simple viewing platform set up on the balcony burst into applause. At this point, the blasting project of the Peak Garden, which is known as the "Asia's No. 1 Blast", was a complete success. After that, it will enter the demolition and clean-up phase for up to 50 days.

 

  It is understood that the top of the hill garden is located in the south side of Zhongshan College, Dongcheng District, Zhongshan City, Zhongshan City, on the east side of the snow road, will be built in the Star City Building. The building to be exploded is 104.1 meters, with a total of 34 floors (including 1 basement), 33.8 meters wide from east to west, 38.5 meters long from north to south, and 27875 square meters. The building is frame-supported shear wall structure, arranged in a “well” shape. The 1st floor and the basement are frame structures, the 2-32 floors are shear wall structures, and the middle part is the core tube. The east side of the building is 44 meters away from the bottom of the slope, the southeast side is 40 meters away from Dongyue Temple; the south side is 5.2 meters away from the wall, only 6 meters away from the nearest residential house; the west side is 81 meters away from the bottom of the slope. The building was built in 1994 and was capped in 1997. For various reasons, the building has not been officially put into use. It has been renamed as the Peak Garden, Yangming Mountain Villa, Star City, and Zhongshan City, but it has never been able to get rid of the fate of the "unfinished". In June 2007, the building was transferred to Zhongshan Changjiang Zhaoye Real Estate Development Co., Ltd. as a whole. In order to cope with the overall planning development of Zhongshan City, accelerate the pace of renovation of the old city, and according to the company's project planning needs, decided to use blasting demolition, the plot will be rebuilt after the demolition.

 

  On February 25, commissioned by the Public Security Bureau of the Ministry of Public Security, the Guangdong Provincial Public Security Department and the Zhongshan Public Security Bureau, the China Engineering Blasting Association hosted a review meeting in Beijing on the “Blasting Demolition Project of the Unfinished Building of the Shijiazhuang Peak Garden in Zhongshan City”. The expert group led by Wang Xuguang, academician of the Chinese Academy of Engineering and chairman of the China Engineering Blasting Association, listened to the briefing and review requirements of the Provincial Public Security Department and the Municipal Public Security Bureau on the blasting project, and introduced the construction plan of the Guangdong Zhongren Group. After questioning and discussion, the review opinions were put forward and the Municipal Public Security Bureau was approved to approve the construction of the project. In order to ensure the safety and success of the blasting demolition project, the Zhongshan Municipal Government has specially set up a coordination headquarters, which is responsible for the organization and coordination of various work of blasting demolition. The Coordination Command has developed a detailed work plan. The Guangdong Zhongren Group has designed a rigorous technical and construction organization plan, and the public security department has implemented a detailed safety alert plan. In view of the fact that the safety of the project is extremely prominent, the potential hazards such as blasting vibration, landing impact vibration, blasting flying stones, noise, dust, etc. are very large, and the command department has especially strengthened the careful consideration of blasting safety. Guangdong Zhongren Group has carried out meticulous and detailed safety protection design. Through multiple protection measures such as direct cover protection, near-body protection and shock-absorbing earth embankment, it ensures that the generated blasting vibration has no influence on the nearest residential houses. The ground reduces the collapse shock caused by the impact on the ground and removes the damage of the blasted flying stone. At the same time, do a good job of noise and dust control measures to minimize the harm to environmental sanitation and people's lives. The command department has convened several coordination meetings and went to the scene to resolve the implementation of related matters. At 4:20 pm on August 5, the test blast was successfully carried out. The parameters of the detonator, explosive and shear wall were tested. The strength of the concrete of the building was tested, which provided a technical reference for the amount of explosives during the final blasting. Taking into account the recent typhoon weather caused by the "Swan" and "Morak", after consulting the meteorological department and the experts of the China Engineering Blasting Association, it is prudent to determine the blasting this morning. After the early preparations, more than 20 relevant departments worked together to explore possible risks and take effective measures to ensure the success of the blast.

 

  According to the expert group's assessment, the blasting project is the highest building in China's current blasting demolition project and belongs to the Class A demolition blasting project. Guangdong Zhongren Group Construction Co., Ltd. has the qualification and experience of the project, especially in 2004. The Zhongyin Building in Wenzhou City, Zhejiang Province, with a height of 93.05 meters was demolished, and the design and construction experience of blasting demolition of high-rise buildings was carried out.” After reviewing the latest information, it can be concluded that the top-floor garden is the second largest building in Asia and the tallest in Asia. The blasting demolition project, which is also the self-transcendence of the company's record of maintaining the height of the national building blasting demolition for many years. It is reported that Guangdong Zhongren Group is affiliated to Guangdong Guangsheng Asset Management Co., Ltd., one of the three major asset management companies supervised by the Guangdong Provincial State-owned Assets Supervision and Administration Commission. It is mainly engaged in the investment, construction and operation management of highways and other infrastructure and real estate and environmental protection projects. . Formerly known as the Guangzhou Military Region Zhongnan Civil Defense Industrial Development Group, Guangdong Zhongren Group has been involved in the engineering blasting industry since its establishment in 1990. It has the first-class qualification for blasting and demolition engineering, and has many famous blasting experts. In recent years, the blasting demolition project of Wenzhou Zhongyin Building (first prize of China Engineering Blasting Association), the Thousand-ton blasting project of Daxigou in Shaanxi, and the one-time blasting demolition of 12 dormitories of Guangzhou Petrochemical General Plant and its plant have been successfully implemented. 68m high large urea prilling tower blasting demolition project, Guangxi Guixi alumina plant site leveling large blasting project (third prize of China Engineering Blasting Association), Dongguan Dongxin Hotel (high 13 floors, won the "big city downtown complex The first-class award for the demolition blasting technology of structural buildings, the 12-storey annex building of the Ramada Plaza in Guangzhou, the blasting demolition of the old buildings in Shiyan, Guangxi, and other large-scale earth-rock blasting projects, showing the exquisite blasting technology. Established a good brand and performance, enjoy a high reputation in the domestic blasting industry.

 

  Peak garden blasting time unchanged

 

Peak garden blasting

 

  Yesterday, two villagers from the village of Qiwan Village in the Eastern District made a special trip to see the hilltop garden that was about to burst.

 

Peak garden blasting

 

  Construction workers fill the blasthole with explosives.

 

  From 2 am to 3 pm yesterday, the Zhongshan Daily reported a series of thunder and lightning over Zhongshan. Coupled with the rain all night, many citizens speculated that the date of the demolition of the Peak Garden at 10:30 am on the 13th may be changed. In the afternoon, the reporter confirmed that Lei and Rain did not have much influence on the preparation before the blast, and the blasting date would not change.

 

  Cui Yunwu, a blasting expert, once said that the necessary conditions for blasting are five consecutive sunny days, and that they are most afraid of thundering in the old days. On the 10th, the whole night is thundering and raining. It seems inevitable to change the blasting time. Yesterday afternoon, the reporter interviewed two blasting experts who were on the scene and commanded by the scene. They all said that the blasting time would not change. "I thought that the rain of the night would go down the wall and affect the blasting connection, but after inspection, there is no problem!" Professor Cui said. As for the huge thunder of the night, some experts said that they were shocked by a cold sweat.

 

  The Peak Garden was filled with explosives yesterday.

 

Peak garden blasting

 

  Check the hardness of the clay used for blasting construction.

 

Peak garden blasting

 

  Yesterday, three large gravel piles were piled up in front of the unfinished building. These sandstone piles will be used for blasting to cushion the building.

 

  Zhongshan Business News reported that there were three long shock-absorbing walls downstairs. On the open space near the building, the workers used a pulley and rope to transport a bag of mud to the upper floor... At 7 o'clock yesterday morning, the top garden The blasting project entered the countdown and the explosives work was officially launched.

 

  ■ Shock absorption and shockproof: New shock absorber wall to prevent mud splash

 

  The reporter saw that a pile of sand piles had been "moved" a few days ago and was flattened on the side of the fence near the snowy road. The three long stone powder damping walls are arranged in turn, and the distance between the two damping walls is similar.

 

  According to Cai Wei, the person in charge of the Peak Garden Blasting Project, in order to prevent safety problems after the collapse of the building, they cleaned the original sand pile and replaced it with three stone powder earthquake walls. According to rough estimates, the damping wall is about 40 meters long, about 3 meters high, and has 2000 cubic meters of stone powder. Experts say that with the addition of sandbags, the damping wall can provide a good shock absorption effect.

 

  "If there is mud, when the building is down, the mud will be thrown out one or two hundred meters away!" A responsible person told reporters about the reasons for switching to the stone powder pile.

 

  According to reports, before the blasting, the stone powder anti-vibration wall will be finally processed. The staff will pile sandbags on the shock-absorbing wall, at least 2 to 3 layers, and the “sandbag layer” is 1.5 to 2 meters wide. The staff also considered putting "clothes" on the shock-absorbing wall for better protection.

 

  In addition, the bare ground between the damping walls will also be safely treated. A protective layer similar to plastic and other materials will cover the ground to prevent mud and gravel from splashing when the building is hit.

 

  ■Loading explosives: The sealing mud is not corrected according to the standard.

 

  "From 6 o'clock in the morning to 11 o'clock on the 13th, the Peak Garden will be on guard for 24 hours." A person in charge told the reporter that the task of the day was to complete the 24th, 23rd, 22nd and 14th, 13th and 12th floors. The charging work of the blasting gap.

 

  The explosives were picked up by the workers, and the filling work was carried out step by step from the 24th floor of the highest gap.

 

  Today, the staff will complete the loading of 1 to 5 floors, and strive to complete the drug within two days. After that, the last connection and protection work will be left.

 

  “There are several national-level blasting experts who are here to guide...” Cai Wei, the person in charge of the blasting project, told reporters. It is reported that Wang Xuguang, chairman of the China Blasting Association and academician of the Chinese Academy of Engineering, will be on the scene of the blasting on the 12th.

 

  "This mud is not good, too thin, you need to change it immediately! You need to add cement!" At 10:15, Professor Liu from the China Blasting Association and Professor Cui Yunwu and several other state-level blasting experts sat on the loading site of the Peak Garden. On the last ring of the drug, several experts were extremely strict. By order, the charge was stopped immediately in the building, and the staff began to dig out the mud in the blasthole and all of them came back.

 

  "Don't work hard for so long, but there is a problem in the final link." Professor Liu told reporters that the mud is used to seal the blasthole. If it can't be sealed, the explosive may be washed out from one side. Instead of exploding to the sides, the energy of the explosive will be partially lost, directly affecting the effect of the blast.

 

  ■ Evacuation of the masses: door-to-door notification of residents in the cordon

 

  The reporter learned that at about 19 o'clock on the same day, the relevant staff members will notify the residents living in the demolition warning line from house to house to prepare for evacuation. Residents and personnel who have evacuated can choose to avoid the danger in the nearest safe area such as Holiday Plaza, the former Power Washing Machine Factory site, and the entrance of the Electronic College of Zhongshan University (College Road).

 

  At 9:45 yesterday, at No. 31 Baizhizhi Street, a small truck was parked in front of the door. Two residents were loading boxes on the car. When the reporter approached, they found that they were equipped with small appliances such as induction cookers and rice cookers. After a while, the two moved a large TV set to the car. The two moving citizens told reporters that they were preparing for the blast ahead of time. In order to prevent them, they moved their valuable appliances to relatively safe relatives.

 

  expert interview

 

  Window glass will not be "frightened" during an explosion

 

  "How much shock will it produce when the building falls down?" asked the reporter.

 

  "For projects like the Peak Garden, the state's collapsed impact touches the ground at 2 to 3 centimeters per second, and according to recent calculations, the shock of the mountain garden is less than 1 cm per second." China Blasting Association Professor Cui Yunwu said.

 

  "Does this kind of shock have any effect on buildings with close distances? Many residents worry that the window glass will be broken due to vibration?" asked the reporter.

 

  "No. The nearby buildings will not be affected as much as this." Cui Yunwu shook his head and told reporters that he was relatively worried about the wall that was a few meters away from the Peak Garden. After the building collapsed, the powerful airflow generated, perhaps It will pose a threat to the nearest wall. This needs to be noted.

 

  According to reports, the impact of the collapse shock to the ground is less than 2 cm per second, which is smaller than the vibration of the container truck.

 

  During the interview, Professor Liu from the China Blasting Association received a number of calls from Wang Xuguang, chairman of the China Blasting Association and academician of the Chinese Academy of Engineering, to ask key questions in the final part of the blast. The reporter learned from the conversation that in order to ensure the smooth progress of the blast, the staff has added a dose to the second floor of the first gap (1 to 5 layers).

 

  "The most important thing is to dump! So the first gap to blow the five-story building has great benefits." Professor Liu told reporters that in general, the protection of the project unit is relatively in place, with 7 layers of protection.

 

  "This explosion has been successfully completed. The Chinese group is expected to win the first prize or even the special prize. After all, this is the highest building in China's current demolition blasting." Professor Liu said.

Scan the QR code to read on your phone

please try again.
The fourth blasting vibration measurement technology seminar was held
BlastingVibrationTestingTechnologySeminar  BlastingVibrationTestingTechnologySeminar   OnApril15-17,2011,ChinaEngineeringBlastingAssociationhelda“BlastingVibrationTechnologySeminar”atButterflyValleyHotelinNanhai,GuangdongProvince.TheconferencewashostedbyChinaEngineeringBlastingAssociation,GuangzhouZhongboSafetyNetTechnologyCo.,Ltd.,YangtzeRiverWaterConservancyThecommitteewasco-organizedbytheYangtzeRiverScientificResearchInstituteandSouthChinaUniversityofTechnology,andGaoYintong,secretarygeneraloftheassociation,presidedoverthemeeting.  ChairmanWangXuguangattendedthemeetingtomakeanimportantspeech   ChairmanWangXuguangattendedthemeetingandmadeanimportantspeech. AcademicianWangpointedout:Atthebeginningofthe12thFive-YearPlan,thesituationinallwalksoflifeisverygood.Thisisagoodpromotionforthedevelopmentofourengineeringblastingindustry,anditalsomakesusfeelacertainpressure. Blastingvibrationmonitoringisamajoreventinourengineeringblastingindustry.ThesafetyaccidentsthattheChinaEngineeringBlastingAssociationhasbeeninvolvedininrecentyearsareallrelatedtotheimpactofblastingvibration.Therefore,theblastingvibrationpropagationlawshouldbewellrecorded,andadatabaseshouldbeestablished.Class,summary,refiningandprocessingcaneffectivelypromotetheresearchofblastingtheoryandpromotethebetterdevelopmentofengineeringblastingindustry.   AcademicianWangreviewedandsummarizedtheresearchworkonvibrationmeasurementintheindustrysincetheChinaEngineeringBlastingAssociation's"StudyontheImpactofBlastingVibrationandTestingTechnology"heldinHangzhouonApril10,2009.WangAcademicianpointedoutthattheChinaAssociationofExplosivesfrom2009SinceAprilofthisyear,threesymposiumsonblastingvibrationtestinghavebeenheld.Thismeetingisthefourthspecialmeeting.Afterthemeeting,thedevelopmentdirectionofindustrialblastingtestingtechnologyandvibrationtestinginstrumentsshouldbeclarifiedandshouldbeimplemented.Apersonisresponsibleforimplementation.   WuXinxia,​​QuGuangjian,GaoYing,HuangYuewen,LongYuan,YangNianhua,GaoWenxue,ChenQiliangandotherexpertsmadespecialspeeches,GuangzhouZhongboSafetyNetTechnologyCo.,Ltd.,SouthChinaUniversityofTechnologyandYangtzeRiverWaterResourcesCommissionChangjiangAcademyofSciencesandotherunitsontheblastingVibrationremotetesting,calibrationandsystemmanagementweredemonstratedanddemonstratedonsite.  ProfessorWuXinxiafromtheYangtzeRiverScientificResearchInstituteoftheYangtzeRiverWaterResourcesCommission  ProfessorQuGuangjianfromGuangzhouZhongboSafetyNetTechnologyCo.,Ltd.  AssociateProfessorGaoYingfromSouthChinaUniversityofTechnology  SeniorEngineerHuangYangwenfromtheYangtzeRiverScientificResearchInstituteoftheYangtzeRiverWaterResourcesCommittee  ProfessorLongYuanfromthePLAUniversityofScienceandTechnology  ResearcherYangNianhuafromChinaAcademyofRailwaySciences  ProfessorofHighLiterature,BeijingUniversityofTechnology  AssociateProfessorChenQiliangfromGuangzhouZhongboSafetyNetTechnologyCo.,Ltd.   ProfessorWuXinxiafromtheYangtzeRiverScientificResearchInstituteoftheYangtzeRiverWaterResourcesCommitteeintroducedtheconstructionconceptandmanagementmodeofthe"DangerDetectionRemoteSensingInformationManagementSystemforEngineeringBlasting"basedontheInternetofThingstechnology,andthecorrespondingblastingremoteintelligentrecorderandblastingvibrationremotecalibrationequipment;GuangzhouZhongboProfessorQuGuangjianofSafetyNetTechnologyCo.,Ltd.introducedtheimportanceofbuildingavibrationmeasurementinformationmanagementsystemandthecomposition,functionandobjectivesofthevibrationmeasurementinformationmanagementsystem,aswellasremotecalibrationtechnology,dataprocessingandmethods;AssociateProfessorGaoYingofSouthChinaUniversityofTechnologyThekeytechnologyofremotecalibrationandvibrationmeasurementplatformbasedonvibrationgridisalsodemonstrated.TheseniorengineerofYangtzeRiverWaterResourcesCommitteeYangYuewenintroducedthecomposition,performanceandremotecalibrationmethodofblastingdatamonitoringsystembasedonInternetofThings.TheproblemwasdiscussedbyProf.LongYuanfromPLAUniversityofScienceandTechnology.Theresearchonthestandardizationofengineeringblastingvibrationtestingtechnologywasintroduced.ResearcherYangNianhuaofChinaRailwayScienceResearchInstituteintroducedthetechnologyoffieldtestingofblastingvibration;ProfessorGaoWenofBeijingUniversityofTechnologyintroducedshallowtunnel Excavationblastingvibrationremotemonitoringsystemandtestingtechnology;AssociateProfessorChenQiliangofGuangzhouZhongboSafetyNetTechnologyCo.,Ltd.takesthewesternpipelineblastingvibrationmonitoringpracticeasanexampletointroducethestepsandcontentsofblastingvibrationmonitoringwork,anddiscussestheblastingvibrationmonitoringtechnologyinthenearApplicationproblemsinpipelineblastingengineering.   Afteraheateddiscussion,theparticipatingexpertsaffirmedthattheapplicationofinformationnetworktechnologyinthefieldofengineeringblastingisthefuturedevelopmenttrend,andputforwardthepreparationofthe"TechnicalTeachingMaterialsforEngineeringBlastingVibrationMeasurementTechnology"and"TechnicalSpecificationsforEngineeringBlastingVibrationInspection(S
Associate Professor Chen Qiliang from Guangzhou Zhongbo Safety Net Technology Co., Ltd.   Professor Wu Xinxia from the Yangtze River Scientific Research Institute of the Yangtze River Water Resources Committee introduced
Announcement:TheMinistryofPublicSecurityissuedtwostandardsforgradingmanagementofblastingoperations   AccordingtotheRegulationsontheSafetyManagementofCivilExplosives,theMinistryofPublicSecurityissuedtwostandardsforthegradingmanagementofblastingoperationsonMay2,2012-"QualificationRequirementsandManagementRequirementsforBlastingOperationUnits"(GA990-2012),Theblastingoperationprojectmanagementrequirements(GA991-2012)(hereinafterreferredtoas"twostandards"),andissuedthe"Noticeontheimplementationoftheblastingoperationunitqualificationconditionsandmanagementrequirements"and"blastingoperationprojectmanagementrequirements"》.   Recently,theMinistryofPublicSecuritywillorganizeandcarryoutnationalpublicityactivities. TheProvincialDepartmentwill,inaccordancewiththespiritoftheMinistryofPublicSecurity'snoticeandtherequirementsofpublicity,combinedwiththepracticeofpublicsecuritymanagementintheblastingoperationindustryofourprovince,carefullystudyandformulatetheimplementationofworksteps,conductresearch,developaworksystem,establishaspecialorganization,andcarryoutimplementationworkinanorderlymanner. Thespecificworkrequirementsaretobenotifiedbytheprovincialgovernment.   AccordingtothenoticeoftheMinistryofPublicSecurity,theworkofcleaningupandrectifyingtheexistingblastingoperationsunitsandissuingthe"BlastingOperationUnitPermit"shallbecompletedbyDecember31,2012. Therefore,asofJanuary1,2013,anyunitmustholdtheBlastingOperationUnitPermittoengageinblastingoperations,otherwiselegalliabilityshouldbepursued. Beforethatdate,theoriginallegal"ExplosivesUsePermit"cancontinuetobeusedbyunitsthathavenotbeenorderedtostoptheiremployment.Thecommercialblastingoperationunitcanstillholdaneffectiveconstructiondepartment"blastinganddemolition"qualification.Thedocumentsareintheprovincetoundertaketheblastingoperationitemsofthecorrespondingtype.   Fromnowon,theprovincewillnolongerapprovetheoriginal"ExplosiveGoodsUsePermit",andthepublicsecurityorganswillstopacceptingtheconditionalreviewworkoftheconstructionandconstructiondepartmententrustedbytheconstructiondepartmentto"blastinganddemolitioncontractingqualifications".   downloadattachment:   1.Noticeontheimplementationofthe"QualificationConditionsandManagementRequirementsforBlastingOperationUnits"and"ManagementRequirementsforBlastingOperationProjects"   2.Qualificationconditionsandmanagementrequirementsoftheblastingoperationunit   3.Blastingoperationprojectmanagementrequirements
Special Report on Demolition Blasting of 104 Meters High Building in Zhongshan City, Guangdong Province
Editor'snote:   ThePeakGardenwasbuiltin1994andwascappedin1997.The34-storeybuildingis344.1metershigh.Itisaframe-supportedshearwallstructure.Itisthetallestbuildingdemolishedbydomesticblastingandhasappliedtobecomethe"Asia'sfirstexplosion".Oneofthefewhigh-risebuildings. ThePeakGardenwasappliedforblastinginFebruarytoofficialblastingonAugust13.Thetimewasupto6months.Thedayswearelookingforwardtoarefinallycoming,andIwishtheChinesepeopleasuccessfulblast!   Joyaftersuccessfulblasting    Figure1   FigureII   Successfulblastingofthetopgarden    PreparetoblastChenShaopantoprovidepictures    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess   ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess  ChenShaopanprovidespicturesoftheblastingprocess   ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess    ChenShaopanprovidespicturesoftheblastingprocess   ChenShaopanprovidespicturesoftheblastingprocess   "Asia'sfirst-explosion"trackingreport-   Unfinished15yearsofplanning   "Asia'sfirstexplosion"     ——Theblastingofthe104.1mhighbuildingofShijiePeakGardeninZhongshan,Guangdong   "Five,four,three,two,one,detonation!"   At10:30onthemorningofAugust13,withtheorderofLiuWen,thechairmanofthesmashingengineeringheadquartersofShijiePeakGarden,thestaffofGuangdongZhongrenGroupConstructionCo.,Ltd.Pressedthepulsedetonatorinyourhand. "嘣,嘣,嘣..."18consecutiveloudnoises,afterashort3.6seconds,atotalheightof104.1meters,atotalof34layersofZhongshanShijiePeakGardenunfinishedbuildingsweighingtensofthousandsoftonsofbody,oneSuddenly,hesuddenly"squats"andsuddenlyrushestowardthewestsideoftheopenspace. Thethreehigh-poweredfireenginesthathavebeenwaitingforalongtimeimmediatelysprayedahugeamountofwatermist,andcarriedout“interceptioninterception”onthedust“whitesmoke”causedbytheexplosion,andsprinkledwatertoreducedust. Congratulationsontheheadquartersofthemeetingroomonthe4thfloorofShunjingGarden,andthesimpleviewingplatformsetuponthebalconyburstintoapplause. Atthispoint,theblastingprojectofthePeakGarden,whichisknownasthe"Asia'sNo.1Blast",wasacompletesuccess. Afterthat,itwillenterthedemolitionandclean-upphaseforupto50days.   ItisunderstoodthatthetopofthehillgardenislocatedinthesouthsideofZhongshanCollege,DongchengDistrict,ZhongshanCity,ZhongshanCity,ontheeastsideofthesnowroad,willbebuiltintheStarCityBuilding. Thebuildingtobeexplodedis104.1meters,withatotalof34floors(including1basement),33.8meterswidefromeasttowest,38.5meterslongfromnorthtosouth,and27875squaremeters. Thebuildingisframe-supportedshearwallstructure,arrangedina“well”shape.The1stfloorandthebasementareframestructures,the2-32floorsareshearwallstructures,andthemiddlepartisthecoretube. Theeastsideofthebuildingis44metersawayfromthebottomoftheslope,thesoutheastsideis40metersawayfromDongyueTemple;thesouthsideis5.2metersawayfromthewall,only6metersawayfromthenearestresidentialhouse;thewestsideis81metersawayfromthebottomoftheslope. Thebuildingwasbuiltin1994andwascappedin1997. Forvariousreasons,thebuildinghasnotbeenofficiallyputintouse.IthasbeenrenamedasthePeakGarden,YangmingMountainVilla,StarCity,andZhongshanCity,butithasneverbeenabletogetridofthefateofthe"unfinished". InJune2007,thebuildingwastransferredtoZhongshanChangjiangZhaoyeRealEstateDevelopmentCo.,Ltd.asawhole. InordertocopewiththeoverallplanningdevelopmentofZhongshanCity,acceleratethepaceofrenovationoftheoldcity,andaccordingtothecompany'sprojectplanningneeds,decidedtouseblastingdemolition,theplotwillberebuiltafterthedemolition.   OnFebruary25,commissionedbythePublicSecurityBureauoftheMinistryofPublicSecurity,theGuangdongProvincialPublicSecurityDepartmentandtheZhongshanPublicSecurityBureau,theChinaEngineeringBlastingAssociationhostedareviewmeetinginBeijingonthe“BlastingDemolitionProjectoftheUnfinishedBuildingoftheShijiazhuangPeakGardeninZhongshanCity”.TheexpertgroupledbyWangXuguang,academicianoftheChineseAcademyofEngineeringandchairmanoftheChinaEngineeringBlastingAssociation,listenedtothebriefingandreviewrequirementsoftheProvincialPublicSecurityDepartmentandtheMunicipalPublicSecurityBureauontheblastingproject,andintroducedtheconstructionplanoftheGuangdongZhongrenGroup.Afterquestioninganddiscussion,thereviewopinionswereputforwardandtheMunicipalPublicSecurityBureauwasapprovedtoapprovetheconstructionoftheproject. Inordertoensurethesafetyandsuccessoftheblastingdemolitionproject,theZhongshanMunicipalGovernmenthasspeciallysetupacoordinationheadquarters,whichisresponsiblefort
Call for papers on participation in the "6th International Conference on Explosives and Blasting Technology of China, Japan and Korea"
Allrelevantunits:   The6thInternationalConferenceonExplosivesandBlastingTechnologyofChina,JapanandKoreawasscheduledtobeheldinSouthKoreafromOctober12to16,2011.Theconferenceincludedexplosives,detonationequipment,geotechnicalblasting,mineblastinganddemolitionblasting. Inordertostrengtheninternationalacademicexchangesandtechnicalcooperation,theChinaEngineeringBlastingAssociationisnowissuingnoticesofessaystorelevantunitsanddepartments.Expertsfromenterprises,institutions,researchinstitutesanduniversitiesarewelcometosignupandactivelycontributetotheconference.   Theessaycontentisasfollows:   1.Callforpapers:   TheauthorisaskedtofirstsubmitanEnglishabstractofabout200to400words(includingthetitleofthearticle,author,unit,contactnumberande-mail)andkeywords. Thebestchoiceis3to5keywords.   Second,thedraftschedule:   (1)DeadlineforsubmissionofEnglishabstracts:July20,2011   (2)DeadlineforsubmissionoffulltextinEnglish:September10,2011   Third,themodeofsubmission:   PleasesendtheEnglishabstracttotheemailaddress:cseb@cseb.org.cnormingxiuzhu@yahoo.com.cn   Contact:ZhuMingxiu   Contactnumber:(010)88399565   Fax:(010)68344564   Contactaddress:No.1WenxingStreet,Xizhimen,Beijing100044
Seven years of honing the "Blasting Net" sharp display
Time of issue : 2019-05-30 10:01:00
TheCoalIndustryPublishingHousepublishedthenewbook"ThePracticalManualforCoalMineBlasting"publishedinApril2008,andintroducedthedetailsof"ZhongboNet"intheentiresectionofChapter23ofChapter23,fullyaffirmingitssafetytothecoalmineblastingindustry.Informationproductionplaysanimportantrole.   ItisenoughtoprovethatundertheleadershipoftheChinaEngineeringBlastingAssociationandthestrongsupportoftheblastingassociationsofvariousprovincesandcities,aftersevenyearsoftempering,intheeraofrapiddevelopmentofinformationtechnology,"ChinaBlastNetwork"hasbecomeChinawithoutanydispute.Theforerunnerofthedevelopmentofinformationizationintheengineeringblastingindustryhasbecomethelinkoftheinformationtransmissionoftheblastingindustryandthecivilexplosiveequipmentindustryandtheinformationcenterfortheacquisitionofrelevantinformation.   "ChinaBlastNetwork"hasbeenrecognizedbytheindustryasthefirstportalsiteoftheblastingindustry. Theloudandmeaningfulnameof"BlastingNet"isonceagainrevealed!   ChinaBlastingNetworkEditorialDepartment   April10,2009

Copyright@ 2002-2018 gzbpw Inc. All Rights Reserved Guizhou blasting network Copyright
Reproduction, abstraction, reproduction or mirror-building are prohibited without authorization.

Website Construction:Motivation of Chinese Enterprises   Guiyang    Guizhou ICP No. 11000840